Wealthier & Fairer - Local Delivery Plan Milestones 31/12/09
|
|
|
Contents :-
Maintain the rate of business start ups 1. Business Gateway 2. Business parks and industrial units Businesses in Moray will grow GVA 3. Account Management Programme 4. Key Action: Moray Towns Partnership Moray will benefit from an improved and safer transport infrastructure 5. Reduce the number of road accidents in Moray 6. Elgin Traffic Management Plan 7. Develop an evidence base to support the case for investment in the A96 and A95 People in Moray will have access to better paid employment 8. Rural Development Strategy 9. Development of a Moray Life Sciences Centre 10. Expand the Apprentice Scheme to all Partners and to include graduates and manual workers
Back
Wealthier& Fairer Local Outcome: Maintain the rate of business start ups Key Action: Business Gateway Overall, Key Action 100% completed. |
| Milestone |
Milestone Due Date |
Milestone Note |
Progress |
| Establish Business Gateway in Moray as the centre for all business enquiries - Q1 |
30 Jun 2009 |
Business Gateway in Moray began operation on 1st April 2009 based at 17 High Street, Elgin. |
100 % |
| To develop and begin a programme of business training workshops on a monthly basis - Q1 |
30 Jun 2009 |
Programme of training workshops developed through a training provider (Consentia) in quarter 1. |
100 % |
| Provide information and advice to at least 80 new or existing businesses during the quarter - Q2 |
30 Sep 2009 |
Provided information and advice to new and existing businesses exceeding 80 in number during quarter 2. |
100 % |
| To have provided assistance and support in the creation of at least 20 new businesses during the quarter - Q2 |
30 Sep 2009 |
Provided assistance and support leading to the creation of 32 new businesses during quarter 2 |
100 % |
| Run a number of business training workshops with a full uptake - Q2 |
30 Sep 2009 |
Ran 18 business workshops during the quarter with near 100% uptake at all workshops. |
100 % |
| Assist and participate in the Open Doors event at Moray College focussed on entrepreneurship and business start up- Q3 |
31 Dec 2009 |
Gave two presentations to students and lecturers at Moray College on 7 October 2009 along with The Prince's Scottish Youth
Business Trust (PSYBT). From this 16 enquiries were received from students interested in finding out more about starting a
small business. |
100 % |
| Provide information and advice to at least 80 new or existing businesses in the quarter - Q3 |
31 Dec 2009 |
Provided information and advice to new and existing businesses exceeding 80 in number during quarter 3. |
100 % |
| To have provided assistance and support in the creation of at least 20 new businesses during the quarter - Q3 |
31 Dec 2009 |
Provided assistance and support leading to the creation of 17 new businesses during quarter 3. In total for quarter 2 and
3 the service has support the creation 59 new businesses in Moray (exceeding overall target of 40) |
100 % |
| Run a number of business training workshops with a full uptake - Q3 |
31 Dec 2009 |
18 Business workshops have been run during quarter 3 with all workshops having been fully booked. The training workshops included
marketing & selling skills, networking skills and record keeping |
100 % |
| Provide information and advice to at least 80 new businesses during the quarter - Q4 |
31 Mar 2010 |
Provided information and advice to new and existing businesses exceeding 80 in number during quarter 4. |
100 % |
| To have provided assistance and support in the creation of at least 20 new businesses during the quarter - Q4 |
31 Mar 2010 |
Provided assistance and support leading to the creation of 11 new businesses during quarter 4. Business Gateway has supported
the creation 83 new businesses in Moray (exceeding overall target of 60 for the year) – 100% overall. |
100 % |
| Run a number of business training workshops with a full uptake - Q4 |
31 Mar 2010 |
17 Business workshops have been run during quarter 4 with all workshops having been fully booked. The training workshops included
marketing & selling skills, E commerce Understanding Finance and record keeping. |
100 % |
Back Top of Page
Wealthier& Fairer Local Outcome: Maintain the rate of business start ups Key Action: Business parks and industrial units Overall, Key Action 85% completed. 6 of the 12 underlying milestones have been completed during 2009/10. The remaining 6
milestones are progressing and have been carried forward to 2010/11. |
| Milestone |
Milestone Due Date |
Milestone Note |
Progress |
| Enterprise Park Forres; report on the progress made with the construction of Science unit - Q1 |
30 Jun 2009 |
Science unit construction progressing. Due to completion by November 2009. |
100 % |
| Buckie Business Park; report on the continued discussions on purchasing land for development with conditional missives - Q1 |
30 Jun 2009 |
Delay in associated planning decisions have resulted in reconfiguration of the proposed site. Missives dependant on satisfactory
conclusion of further professional advice e.g. valuation. Milestone carried forward to year 2010/11 |
50 % |
| Elgin West Business Park; report on the site investigation - Q1 |
30 Jun 2009 |
Elgin West site investigations due for completion by end of October 09. Access to site delayed. |
100 % |
| Enterprise Park Forres; report on the progress made in the construction of the Science unit. Begin to outline refreshed inward
investment propositions to attract businesses and activity to the area - Q2 |
30 Sep 2009 |
Science building construction still going according to plan and on budget. Completion due in November 09. Some interest exhibited
but no agreement to lease to date. Revised promotional plan for Enterprise Park Forres due by end of November 09. |
100 % |
| Buckie Business Park; conclude conditional missives in purchasing of land for development - Q2 |
30 Sep 2009 |
Delay in associated planning decisions has resulted in reconfiguration of the proposed site. Planning application to TESCO
approved 29/09/09. HIE now progressing discussions with landowner and due diligence. Milestone carried forward to year 2010/11 |
50 % |
| Elgin West Business Park; conclude initial site investigations - Q2 |
30 Sep 2009 |
Site investigation and report due to conclude mid October 09. Outcome will advise HIE of potential site valuation and indicative
yield on investment. |
100 % |
| Enterprise Park Forres; completion of the 10,000 square foot Science unit. Complete the refreshment of inward investment
propositions to attract businesses and activity to the area - Q3 |
31 Dec 2009 |
Building completed and awaiting handover from contractor following commissioning of heating systems etc. Already engaged in
discussion with company who are considering moving into this completed unit. |
100 % |
| Buckie Business Park; produce detailed design and apply for planning permission |
31 Dec 2009 |
Detailed design almost completed. Submission for planning permission postponed until missives progressed. Milestone carried
forward to year 2010/11. |
80 % |
| Elgin West Business Park; begin to negotiate conditional missives for purchasing of land for development - Q3 |
31 Oct 2009 |
Now working on detailed design of park layout. Discussions with Transport Scotland critical to feasibility of site. Milestone
carried forward to year 2010/11. |
80 % |
| Enterprise Park Forres; begin to implement inward investment marketing communications - Q4 |
31 Mar 2010 |
Contract tendered and awarded and marketing programme started. |
100 % |
| Buckie Business Park; produce detailed design and apply for planning permission - Q4 |
31 Mar 2010 |
Detailed design almost completed. Submission for planning permission postponed until missives progressed. Milestone carried
forward to year 2010/11. |
80 % |
| Elgin West Business Park; seek to conclude conditional missives for purchasing land for development - Q4 |
31 Mar 2010 |
Now working on detailed design of park layout. Discussions with Transport Scotland critical to feasibility of site. Milestone
carried forward to year 2010/11. |
80 % |
Back Top of Page
Wealthier& Fairer Local Outcome: Businesses in Moray will grow GVA Key Action: Account Management Programme Overall, Key Action 100% completed. |
| Milestone |
Milestone Due Date |
Milestone Note |
Progress |
| Identification, development and delivery of growth plans and associated projects with businesses of significant growth potential
in Moray, and report on progress made by end of quarter- Q1 |
30 Jun 2009 |
Moray Area Office to agree 26 growth plans with businesses of growth potential and 10 growth plans for Social Enterprises
by the end of March 2010. At the end of Quarter 1 five business growth plans agreed and three Social Enterprise plans agreed.
Projects being assessed on research and development activity, building grant for expanded premises, Capex for plant and machinery
and Management and Development training for senior and supervisory staff. |
100 % |
| Continue development and delivery of growth plans and associated projects, reporting on progress made by end of quarter -
Q2 |
30 Sep 2009 |
At the end of period 2 five business growth plans agreed and five Social Enterprise plans agreed. Eleven business support
projects approved at a combined value of £466k. Types of approval range from R&D grant. Building grant, Assistance to tourism
group and graduate placement. Projected to rise to 16 plans agreed by mid November 09 and to 26 by end of March 09 with GVA
of £21m. |
100 % |
| Continue development and delivery of growth plans and associated projects, reporting on progress made by end quarter - Q3 |
31 Dec 2009 |
At the end of quarter three we have 18 businesses growth and 5 social enterprise growth plans agreed. We are currently processing
several applications for grant assistance in support of previously agreed growth strategies. On the basis of what we currently
understand we expect to achieve our target of 26 business growth plans by the end of March 2010. |
100 % |
| Continue development and delivery of growth plans and associated projects, reporting of progress made by end of quarter -
Q4 |
31 Mar 2010 |
HIE staff have worked with businesses engaged in export to develop detailed three year growth strategies. There are now 53
businesses and 10 social enterprises with growth plans in place. In the past 12 months 35 finance projects were approved to
deliver that growth. There was also wide ranging support activity including workforce and market development, provision of
market intelligence, strategy workshops, sign posting, networking leads etc. |
100 % |
| Report on annual yield generated against Moray GVA for 2009/10 - target of 21M yield by 2011/12 |
31 Mar 2010 |
The anticipated yield over the next three years for the growth plans agreed this year (27 in number) is £26.8 million of gross
value added. |
100 % |
Back Top of Page
Wealthier& Fairer Local Outcome: Businesses in Moray will grow GVA Key Action: Moray Towns Partnership Overall, Key Action 91% completed. 10 of the 17 underlying milestones have been completed during 2009/10. The remaining
milestones are generally well progressed and due to be completed in the near future. |
| Milestone |
Milestone Due Date |
Milestone Note |
Progress |
| Begin implementation of marketing/tourism projects that received match funding through LEADER - Q1 |
30 Jun 2009 |
Projects that received Leader match funding are either completed or well under way. |
100 % |
| Publication and distribution of 'Tear off Town Maps' and leaflets to promote and improve information for visitors to Lossiemouth
and Forres - Q1 |
30 Jun 2009 |
‘Tear off Town Maps’ and Leaflet projects have been completed for Lossiemouth and Forres. |
100 % |
| Preparation and submission of Scottish Government Town Centre Regeneration Fund for match funding for a number of Partnership
projects - Q1 |
30 Jun 2009 |
The first bid to the Scottish Government Town Centre Regeneration Fund for match funding for a number of Partnership projects
was submitted on time, however the bid was unsuccessful. A bid for the second round of funding has been submitted and currently
awaiting outcome. |
100 % |
| Publication and distribution of Business Directory/Handbook aimed at improving marketing of local businesses in Keith - Q2 |
30 Sep 2009 |
Keith Area group assessed situation and have divert resources to the Visitor Information Point Scheme. |
100 % |
| Publication and distribution of Business Directory/Handbook aimed at improving marketing of local businesses in Lossiemouth
and Forres - Q2 |
30 Sep 2009 |
Both Forres and Lossiemouth Handbooks has been produced and being distributed. |
100 % |
| Keith - production of Leaflet wallets to help improve marketing of Keith - Q2 |
30 Sep 2009 |
Keith Information Wallets have been produced and distributed to Visitor Information points. |
100 % |
| Investigate future funding sources for Phase 2 of Moray Towns Partnership - Q2 |
30 Sep 2009 |
A committee report was submitted to Aprils ED&I Committee requesting funding for the Moray Towns Partnership for a further
2 years and was approved. |
100 % |
| Formation of the Buckie Business Association - Q2 |
30 Sep 2009 |
Buckie Business Association has been formed. |
100 % |
| Lossiemouth - installation of 3 map boards to show walks between East and West beach, improving tourist facilities and information
- Q3 |
31 Dec 2009 |
The Map board is currently being designed and will be installed by the end of May. |
40 % |
| Keith - promotion of Farmers/Continental Market and improvements and decorations on Mid Street. Both schemes to attract shoppers
and visitors to Keith - Q3 |
31 Dec 2009 |
Contractor was appointed and has completed consultation work and art work. Contractor is awaiting proofs from printer and
final checks with group (March 2010). Planning applications have been submitted for all 4 towns for Markets. |
90 % |
| Forres - carry out a feasibility study and produce detailed plans on promotion of 'be a disabled-friendly town', improving
access throughout the town - Q3 |
31 Dec 2009 |
Feasibility Study has been completed and is currently being publicised. (March 2010) |
100 % |
| Forres - production and installation of information boards - marking the start of the coastal walk - to improve tourist information
- Q3 |
31 Dec 2009 |
Information Board is being sent to manufacture. (March 2010). |
85 % |
| Buckie - production and distribution of Buckie eco-shopping bags; establishment of Buckie website; and promotion of events
including Art events and Buckie Festival - Q3 |
31 Dec 2009 |
The Buckie eco-shopping bags have been produced and distributed, website established and promotion of Buckie events including
Art events and Buckie Festival. |
100 % |
| Lossiemouth - Ramsay Mac Donald Viewpoint upgrades, enhancing visitor facilities - Q4 |
31 Mar 2010 |
Due to unforeseen weather conditions building work was delayed but is due to be completed by the 17th June if not before.
Mosaic work has been completed. |
80 % |
| Forres - programme of shop front improvement aimed at improving appearance of town centre - Q4 |
31 Mar 2010 |
Forres re-wiring project has been completed and a number of premises took advantage of the Towns Centre Regeneration Fund. |
95 % |
| Buckie - development of Buckie Community Radio; extension of the Speyside Way to Buckie; promoting Buckie as a terminus/start
of 'The Speyside Way' - Q4 |
31 Mar 2010 |
Community Radio - progress being made with developing project including volunteers and location search. Speyside Way - orders
have been placed for necessary equipment to extend walk. |
70 % |
Back Top of Page
Wealthier& Fairer Local Outcome: Moray will benefit from an improved and safer transport infrastructure Key Action: Reduce the number of road accidents in Moray Overall, Key Action 100% completed. |
| Milestone |
Milestone Due Date |
Milestone Note |
Progress |
| Develop and agree set of performance information to be reported to the Wealthier and Fairer Strategic Group on a quarterly
cycle - Q1 |
30 Jun 2009 |
The Road Safety Business Plan for 2009/10 has been developed and includes performance information to be reported to Wealthier
& Fairer Groups quarterly. |
100 % |
| Establish a programme of Road Safety education and training for coming year, targeting schools and general public-Q1 |
30 Jun 2009 |
The Road Safety Business Plan for 2009/10 has been developed and includes a programme of Road Safety education and training
for the year. |
100 % |
| Carry out Road Safety education and training initiatives as set out in programme, reporting on events and attendances - Q2 |
30 Sep 2009 |
During the first 2 quarters of 2009/10, 44 S6 pupils have received "Driving Ambition" training and 16 young people have attended
"Young Drivers" training days. 22 schools have been visited and 1000 persons educated on the "Belt up in Moray" initiative
and 80 people attended "Hot Strike" events. A total of 30 drivers have been warned regarding antisocial driving with 3 vehicles
have been seized. |
100 % |
| Report quarterly performance data to Wealthier and Fairer Strategic Group - Q2 |
30 Sep 2009 |
Performance for quarters 1 and 2 will be reported to the Wealthier and Fairer Strategic Group on 3rd December 2009. |
100 % |
| Carry out Road Safety education and training initiatives as set out in programme, reporting on events and attendances - Q3 |
31 Dec 2009 |
During the third quarters of 2009/10, 340 S6 pupils have received "Driving Ambition" training and 15 young people have attended
"Young Drivers" training days. 755 S5 pupils (all Moray S5) have attended the 'Safe Drive Stay Alive' presentation in Aberdeen.
30 young drivers in Buckie targeted as part of the 'Proactive Hotstrike' Initiative. A total of 22 young drivers have been
warned regarding 'antisocial driving' and 1 vehicle has been seized. |
100 % |
| Report quarterly performance data to Wealthier and Fairer Strategic Group - Q3 |
31 Dec 2009 |
This will be reported through the 'Safer and Stronger' Coordinating Group on 17 February 2010. |
100 % |
| Report on the outcomes of Operation Taurus - regards the combating of drink/drug driving in Moray - Q3 |
31 Dec 2009 |
6 Operation Taurus Initiatives carried out across Moray during quarter 3. This resulted in 451 vehicles being stopped and
146 drivers being breath tested. 1 positive breath test. Comparing quarter 1 to 3 2008/09 to the same period 2009/10, drink
drive detections are 8% down despite an increase in breath tests through Operation Taurus. |
100 % |
| Carry out Road Safety education and training initiatives as set out in programme, reporting on events and attendances - Q4 |
31 Mar 2010 |
Operations conducted and performance report to be submitted to Wealthier and Fairer Group once statistical analysis and end
of year figures confirmed. |
100 % |
| Report quarterly performance data to Wealthier and Fairer Strategic Group - Q4 |
31 Mar 2010 |
Complete and delivered on an ongoing basis |
100 % |
| Annual report on the progress made against suite of performance indicators and outcomes agreed - Q4 |
31 Mar 2010 |
Performance report to be submitted to next Wealthier and Fairer Group once statistical analysis and end of year figures confirmed. |
100 % |
Back Top of Page
Wealthier& Fairer Local Outcome: Moray will benefit from an improved and safer transport infrastructure Key Action: Elgin Traffic Management Plan Overall, Key Action 71% completed. 5 of the 9 underlying milestones have been completed during 2009/10. Exception comments
have been provided in the main report to highlight milestones slippage. The milestones are being carried forward to 2010/11. |
| Milestone |
Milestone Due Date |
Milestone Note |
Progress |
| Issue tenders for Consultant to push forward Elgin Traffic Management Plan - Q1 |
30 Jun 2009 |
Tender issued for term contract. |
100 % |
| Completion of Reiket Lane bridge replacement - Q2 |
31 Aug 2009 |
Reiket Lane Bridge complete. Opened to traffic on 24 July. |
100 % |
| Award contract for Consultant procurement - Q2 |
30 Sep 2009 |
Contract awarded on 1 September 2009. |
100 % |
| Carry out initial ground investigation for Roads, High School and Housing projects - Q2 |
30 Sep 2009 |
Ground investigations completed early September. Final report on testing awaited. |
100 % |
| Completion of design works for Edgar Road extension/Access to High School - Q3 |
31 Dec 2009 |
Design substantially complete. Proposed works at High School have been deferred therefore the decision was taken to review
the requirements for Edgar Road extension, the need for a access to future affordable housing and the requirement for a possible
Western Distributor Road. On hold pending report on the Western Distributor Road and the need for an access to affordable
housing. |
100 % |
| Report on Elgin Traffic Model update - Q3 |
31 Dec 2009 |
Work is ongoing on the Elgin traffic Model through Jacobs Consultants. A report has not been provided due to other higher
priority works, in particular where money from external parties was to be spent by the end of the financial year. |
90 % |
| Award tender for Edgar Road extension/Access to High School - Q4 |
28 Feb 2010 |
Proposed works at High School have been deferred therefore the decision was taken to review the requirements for Edgar Road
extension, the need for a access to future affordable housing and the requirement for a possible Western Distributor Road.
On hold pending report on the Western Distributor Road and the need for an access to affordable housing |
0 % |
| Develop the Elgin car parking strategy - Q4 |
31 Mar 2010 |
This was deferred as it had less priority than other parts of the project which completion using 2009/10 funding. A pilot
study will be carried out in 2010/11 and an assessment made whether to proceed to full scale study and strategy after that. |
0 % |
| Report on the development of the Western Distributor Road Options A&B - Q4 |
31 Mar 2010 |
Consultants are working on the option appraisal. Workshop with consultants and officers was delayed twice due to bad weather.
This took place on the 26th March. Reports to service committee are likely in August and December 2010 and seeking approval
to progress to consultation, with a report on route preference in March 2011.
|
50 % |
Back Top of Page
Wealthier& Fairer Local Outcome: Moray will benefit from an improved and safer transport infrastructure Key Action: Develop an evidence base to support the case for investment in the A96 and A95 Overall, Key Action 98% completed. 6 of the 7 underlying milestones have been completed during 2009/10. |
| Milestone |
Milestone Due Date |
Milestone Note |
Progress |
| Collate classified traffic flow information and traffic crash data for the A95 and A96 routes - Q1 |
30 Jun 2009 |
Complete. |
100 % |
| Engage with Transport Scotland officers to examine A96 options in Elgin - Q1 |
30 Jun 2009 |
Engagement with Transport Scotland officers to investigate A96 options has been carried out. |
100 % |
| Complete Transport Scotland liaisons and agree an action list - Q2 |
30 Sep 2009 |
Concluded liaisons with Transport Scotland with the agreement on an action list. |
100 % |
| Meet with Minister for Transport to discuss and promote proposals for A96 in Elgin - Q2 |
30 Sep 2009 |
Proposals for investment and development of the A96 in Elgin were discussed with Minister for Transport Stewart Stevenson
MSP on the 7th October 2009. |
100 % |
| Carry out outline road survey on A95 - Q3 |
31 Dec 2009 |
All survey work which is required on A95 has been carried out. |
100 % |
| Estimate volumes of goods from major Moray businesses on A95 - Q3 |
31 Dec 2009 |
This is now complete. Summary of results has been circulated to members of the Wealthier & Fairer Group on 18 March 2010. |
100 % |
| Compile a report for submission to Transport Scotland identifying and supporting the need for A95 road improvements - Q4 |
31 Mar 2010 |
The project involving A96 and A95 has shifted in emphasis since the outset. More work and resources than anticipated have
been committed to the A96. A draft report for submission to Transport Scotland identifying and supporting the need for A96
& A95 road improvements will now be completed by end June 2010. |
90 % |
Back Top of Page
Wealthier& Fairer Local Outcome: People in Moray will have access to better paid employment Key Action: Rural Development Strategy Overall, Key Action 100% completed. |
| Milestone |
Milestone Due Date |
Milestone Note |
Progress |
| Establish the LEADER team and Local Action Group (LAG) - Q1 |
30 Jun 2009 |
The LEADER Local Action Group has representatives from the following groups - Highlands and Islands Enterprise Moray, Scottish
Natural Heritage, Forestry Commission Scotland, Scottish Rural Property and Business Association, National Farmers' Union,
Moray Business Women, Moray Voluntary Service Organisation, Joint Community Council Moray, Moray Forum, Grampian Police, NHS,
Moray Federation of Community Halls and Associations.
The Economic Development and Infrastructure Committee (26/05/09) have been asked to consider elected member representation
on the Local Action Group. |
100 % |
| Approve at least £120,000 of LEADER funding to local projects - Q1 |
30 Jun 2009 |
Target exceeded, 7 projects approved with commitment of over £150, 000 of LEADER funds. |
100 % |
| Carry out at least 5 LEADER presentations to Community Groups to promote awareness and applications - Q1 |
30 Jun 2009 |
Target exceeded, 11 presentations delivered. |
100 % |
| Receive at least 25 initial enquiries from interested applicants, offering advice and guidance as appropriate - Q1 |
30 Jun 2009 |
Target met, 25 enquiries received and advice delivered. |
100 % |
| Approve at least £80,000 of LEADER funding to local projects - Q2 |
30 Sep 2009 |
Target exceeded, 9 projects approved with a commitment of over £290,000 of LEADER funds. |
100 % |
| Recruitment of a LEADER Administrative Assistant/Development Officer - Q2 |
30 Sep 2009 |
Target met. Recruitment of an Administrative Assistant/Development Officer on 11 August 2009. |
100 % |
| Carry out at least 5 LEADER presentations to Community Groups to promote awareness and applications - Q2 |
30 Sep 2009 |
Target exceeded, 6 presentations delivered. |
100 % |
| Receive at least 25 initial enquiries from interested applicants, offering advice and guidance as appropriate - Q2 |
30 Sep 2009 |
Target met, 25 enquiries received and advice delivered. |
100 % |
| Approve at least £50,000 of LEADER funding to local projects - Q3 |
31 Dec 2009 |
Target for the quarter was not met, with £30,192 approved against target of £50,000. However, over £450,000 had been approved
at the end of quarter3, exceeding the target of £250,000. Programme Manager devoted a significant amount of time in consultation with the Scottish Government during this quarter. Due
to the time devoted to the consultation regarding proposed changes to the LEADER programme including a significant increase
in funding day to day promotion of the programme slipped. This should be rectified by the establishment of the website and
the consultation moving on to LAG chairs. |
100 % |
| Carry out at least 5 LEADER presentations to Community Groups to promote awareness and applications - Q3 |
31 Dec 2009 |
20 presentations have been delivered at the end of quarter 3, exceeding the target of 15 (5 per quarter).
|
100 % |
| Receive at least 25 initial enquiries from interested applicants, offering advice and guidance as appropriate - Q3 |
31 Dec 2009 |
Target met, 25 enquiries received during quarter 3 with advice delivered. |
100 % |
| LEADER website to go live and marketing material to be published - Q3 |
31 Dec 2009 |
The new website went live on 16 November 2009 and contains details of eligibility criteria, the application process, approvals
to date, news and events and contacts for the Moray LEADER team. |
100 % |
| Continue to establish operational procedures and systems to run, monitor and evaluate programme - Q3 |
31 Dec 2009 |
Target met. Processes and procedures have been put in place and assessed by The Moray Council Audit and Scottish Government
Rural and Inspections Directorate staff. |
100 % |
| Begin to carry out monitoring and evaluation of successful applications to ensure projects are achieving - Q4 |
31 Mar 2010 |
The LEADER team are continually monitoring the progress of all projects approved in the previous year. All claim forms must
include a project progress report and so far 4 claims have been processed with payments going to the applicants. Project monitoring,
including site visits will continue as an ongoing core activity of the programme. |
100 % |
| Approve at least £50,000 of LEADER funding to local projects - Q4 |
31 Mar 2010 |
Target met, 7 projects approved with a commitment of over £170,000 of LEADER funds in quarter 4. |
100 % |
| Carry out at least 5 LEADER presentations to Community Groups to promote awareness and applications - Q3 |
31 Mar 2010 |
23 presentations have been delivered at the end of quarter 4, exceeding the target of 20 for the year. |
100 % |
| Receive at least 25 initial enquiries from interested applicants, offering advice and guidance as appropriate - Q4 |
31 Mar 2010 |
Target met, 29 enquiries received during quarter 4 with advice delivered. |
100 % |
Back Top of Page
Wealthier& Fairer Local Outcome: People in Moray will have access to better paid employment Key Action: Development of a Moray Life Sciences Centre Overall, Key Action 30% completed. 1 of the 5 underlying milestones has been completed during 2009/10. Exception comments
have been provided in the main report to highlight milestones slippage. The milestones are being carried forward to 2010/11. |
| Milestone |
Milestone Due Date |
Milestone Note |
Progress |
| Outline of Moray Life Science Centre Business Case to be developed - Q1 |
30 Jun 2009 |
The Moray Life Science Centre Business Case complete and agreed by the Board of Moray College in June 2009. £3m of ERDF has
already been secured, Moray College has committed its share of the £9.75m cost, and HIE Moray have approved £1.5m on the basis
of the business case. NHS Grampian's £3.5m contribution presents some difficulty for the Board at a time of decreasing capital
funding and growing demands. |
100 % |
| Appointment of Project Manager and Design Team - Q2 |
31 Jul 2009 |
Moray College has taken on this role until now but this now has to be undertaken by a project specialist. Positions of Project
Manager and Design Team members have been advertised and tenders received. Decision taken not to appoint until greater certainty
in relation to funding. All going well, the Project Team should be in place by June 2010. |
50 % |
| Design Development RIBA Stage D - Q2 |
30 Sep 2009 |
Decision taken not to proceed to next stage until funding secured from all partners. Revised due date of September 2010. |
0 % |
| Technical Design RIBA Stage E - Q3 |
31 Dec 2009 |
See earlier comment |
0 % |
| Commence Pre-Construction RIBA Stage F-H - Q4 |
31 Mar 2010 |
See earlier comment |
0 % |
| |
Back Top of Page
Wealthier& Fairer Local Outcome: People in Moray will have access to better paid employment Key Action: Expand the Apprentice Scheme to all Partners and to include graduates and manual workers Overall, Key Action 85% completed. 12 of the 16 underlying milestones have been completed during 2009/10. Exception comments
have been provided in the main report to highlight milestones slippage. |
| Milestone |
Milestone Due Date |
Milestone Note |
Progress |
| Advertise and start recruiting process for 2nd group of apprentices as part of the Moray Council Apprentice Scheme - Q1 |
30 Jun 2009 |
Adverts were placed in June 2009 for a second batch of apprentices as part of the Moray Council apprentice scheme. 12 were
recruited, and started on 7th September 2009. |
100 % |
| Negotiate trainee/graduate opportunities with service managers where there has been difficulty in filling professional posts
- Q1 |
30 Jun 2009 |
Worked with a small number of departments who may be able to release funding from existing posts for new trainee positions.
Trainee Building Standards Officer appointed, Trainee Monitoring Officer (Env. Protection) appointed. |
100 % |
| Progress report on the 1st group (recruited Jan 2009) of Moray Council apprentices - Q1 |
30 Jun 2009 |
Progress on the first group of Moray Council apprentices was reported to Policy and Resources Committee on 25th August 2009.
By July 2009 all 11 had commenced ECDL, and 3 had completed all 7 units. Also by July, all 11 had commenced their SVQ, and
are on schedule with this qualification. An SVQ external examiner recorded a very satisfactory assessment of the training
procedures and documentation taking place. Positive feedback has been received from both managers and apprentices. 6 apprentices
have been invited to the European Youth Parliament in Elgin's twin town, Landshut, in October. |
100 % |
| Explore opportunities of other funding bodies to develop further schemes that will benefit young people - Q1 |
30 Jun 2009 |
Worked with FSF Manager to promote new scheme that will be aimed at more vulnerable young people, long term unemployed and
Looked After Children. Funding applications completed. |
100 % |
| Recruit and place 2nd group of apprentices (minimum of 11) in operational areas - Q2 |
30 Sep 2009 |
12 new apprentices began their employment under the Moray Council apprentice scheme on 7th September 2009. They have been
placed in the following services: ICT, Elgin; Sport-Leisure, Keith; Business Continuity, Elgin; Sports Development; Elgin,
Legal, HQ Elgin; Chief Executive's Office (2), Elgin; Transportation, Academy Street, Elgin; Committee Services, Elgin; Registrars,
Elgin; Youth Development; Housing P&D, HQ Elgin. |
100 % |
| Develop 'buddy system' with 1st group of apprentices to develop a network of young staff to offer further support and encouragement
- Q2 |
30 Sep 2009 |
Each of the apprentices now has a 'buddy'. They have had an initial meeting followed on 25th Sept. |
100 % |
| Organise meeting with community partners to discuss opportunities for partners to introduce apprenticeship scheme within their
agency - Q2 |
30 Sep 2009 |
Further discussions with community partners have resulted in delays in expanding scheme. This is largely due to the extreme
financial pressures facing all partners (inc. Moray Council). |
100 % |
| Advertise and recruit for Apprentice Joiner, Plumber and Electrician - Q2 |
30 Sep 2009 |
Housing DLO has successfully recruited 3 new apprentices into Summer 2009. |
100 % |
| Progress report on the 1st group of Moray Council apprentices - Q3 |
31 Dec 2009 |
All apprentices from Group 1 (Jan 09) making good progress. All ICS awards awaiting finished and awaiting assessment. 9 x
ECDL passports completed, further 2 almost completed. Have started and completed 3 elements of the 8 required for SVQ. No
leavers and all wishing to remain in post |
100 % |
| Progress report on the 2nd group of Moray Council apprentices - Q3 |
31 Dec 2009 |
All apprentices from Group 2 (Sept 09) making progress. 3 x ECDL passports completed 7x making progress and 3 not as yet started.
No ICS (Institute of Customer Services) from January 2010 - new programme CSP to run from April 2010. One apprentice undertaking
Sports Development HNC made good start. Slow starts to the SVQs. |
100 % |
| Provide additional training to ensure relevant qualifications are being progressed eg ECDE, ICS, CSP etc - Q3 |
31 Dec 2009 |
One apprentice undertaking Assessor qualification (A1) to be externally assessed 29 January 2010. One apprentice undertaking
Registrars training, One apprentice undertaking Council Tax / revenues training, One apprentice recently changed department
one apprentice undertook work placement in Personnel, several apprentices working in new sections within established departments. |
80 % |
| Explore potential of school visits with partners to showcase job/career opportunities in Moray across a range of employers
- Q3 |
31 Dec 2009 |
A successful visit was undertaken at Keith Grammar school. Focus of current and future visits to schools is to prepare students
for job interviews etc. and not on showcasing job/career opportunities due to the current slowdown in the job market. |
30 % |
| Advertise for 3rd group (2010/11) of apprentices - communicating with Careers Scotland and all Moray secondary schools. Encourage
applications from all school leavers regardless of academic achievements - Q4 |
31 Mar 2010 |
Will have to freeze the programme for the moment. We still have two groups working within the council and the budget will
not support any further apprentices at this time. In the circumstances we will not be advertising specific posts in schools
but will continue to talk to school leavers about careers in local government. |
0 % |
| Develop a structure that will appoint trainee/graduates where there has been difficulty in filling professional posts - Q4 |
31 Mar 2010 |
Further research being taken to explore how development posts in council services are recruited. |
50 % |
| Report on progress of the 2nd group of apprentices on completing SVQs and developing ideas for further career development
- Q4 |
31 Mar 2010 |
Most apprentices have completed or nearing completion of ECDL. All group 2 apprentices have started SVQ, HNC awards. Diverse
range of subjects will require closer scrutiny of progress. |
100 % |
| Report on 1st group of apprentices in maturation stage - focussing on operational aspirations - Q4 |
31 Mar 2010 |
All group 1 apprentices finished ECDL. All group 1 apprentices completed ICS award scheme. Three apprentices completed SVQ3.
Four apprentices almost completed. Four apprentices making steady progress. |
100 % |